The new signalling and telecommunications system has been set up in the railway section Thessaloniki- I've seen her.
This is a development that marks the completion of a strategic project for rail safety and strengthening the country's international freight role.
The project was implemented through the PM 713 contract, which signed in March 2022 and included the installation of a new signalling system throughout the line from Thessaloniki TX1 to Idomeni, the replacement of 37 track changes at critical points of the network, as well as the installation of ETCS Level 1.
ARTICLE CONTINUES AFTER ADVERSION

Enable signaling and telemanaging in Thessaloniki-Eidemen / Photo: Intime
Added 75 km of modern signalling and telegovernment
With its completion, approximately 75 km of modern signalling and telecommunications are added to the main railway line connecting Greece and Europe.
The new system replaces what had been installed in the late 1980s and had been phased out since 2005.
Upgrade reducing transport time
The upgrading of the line to the northern border strengthens the international character of the Greek rail network, providing the possibility of direct route of freight trains from Thriasio to Idomeni and to Europe, without requiring the compulsory bypass until the entrance of Thessaloniki Railway Station before continuing their international route.
ARTICLE CONTINUES AFTER ADVERSION
The new capacity reduces transport time and enhances the competitiveness of the country's main freight corridor.
Kyranakis: Safety and reliability of rail transport - Restore infrastructure
In a statement, Deputy Transport Minister Constantine Kyranakis said:
«The activation of signalling and telemanagement in the Thessaloniki-Eidemeni department, after twenty years, adds 75 km of modern traffic control and management systems to the national network, enhancing the safety and reliability of rail transport.
The value of the project, however, exceeds this line. With the completion of the works in Thessaly by the end of the summer a modern railway corridor will be created that will allow direct freight from Thriasio to Europe.
Step by step we restore critical infrastructure and restore the Greek railway to the map of European transport, proving in practice that we keep our promises».
Palios: An important milestone for modernizing the Greek railway - Continue consistently
For his part, the CEO of the Greek Railways, Christos Palios, said:
ARTICLE CONTINUES AFTER ADVERSION
«The reopening of the signalling and telegovernment in Thessaloniki-Eidmenis is an important milestone for the modernization of the Greek railway.
With the completion of the project, the country's main rail portal to Europe is given operation, strengthening both traffic safety and the development of international freight transport.
We continue consistently the effort to upgrade critical infrastructure that for years remained behind, so that the network meets the modern needs of transport and freight transport».